News
Listening for Life Centre Build
Dated: 22/10/2010
Here is an account of how the Listening for Life Centre took shape during 2008 and 2009.
UPDATE 02/05/08
The Lord Mayor of The City Bradford dug the first sod on 21st February. Site clearance started in March and in May all the steel work has been erected.
The roof is planned for July and main build ready for completion in November. Fitting out the IT facilities will take us to Christmas. Hopefully we will move in in January '09
UPDATE 04/08/08
York House construction remains on target with the building of the new centre. A milestone was achieved when Cr. Robin Owens, former Lord Mayor of Bradford laid the foundation stone at a ceremony on 30th July. The Ear Trust was one of his charities he supported during his term of office 2007.
UPDATE 10/11/08
The rather damp summer did not help the progress of the build. The potential completion date has slipped slightly to 19th December. Once handed over there is still allot of work to do. York House Construction has been excellent in the advice they have given. The overall project is being managed by TMP Associates. Planning is in hand to co-ordinate a move during January.
UPDATE 07/02/09
Very unexpectedly our builders went into receivership at the end of November, a fall out of the Icelandic bank issues.
We had hoped to complete and were on target to have the building handed over on 19th December. Fortunately, with great support we are pleased that Clegg construction came to our rescue. Building works started again on the 12 January and the complex task of completing the audiological booths, wiring in all the data connections and the start of the final 'fixes' are back on track. We hope to have access towards the end of February. It will take a sort while to get the clinics installed.
UPDATE: THE FINAL PHASE
Clegg construction forged ahead during the first 3 months of 2009. It is surprising to see that the whole site can be transformed from a typical builder's yard into a majestic landscaped instantaneous garden literally over night.
Transformations occurred when the tarmac and stone paving was laid. At the same time the grass was rolled out and bushes planted.
The move across from the old unit took place over a weekend during March and with minimal disruption to the clinical activity.